The Renovated Terminal 1
The project's description
The Renovated Terminal 1
5 execution contractors, 10 months of work, 15,000 square meters
Shortening work time by cutting 3 months off the original schedules.
Terminal 1 Upgrade and Preparation Project at the International Flights Airport.
Terminal 1 will be used by passengers for the Low Cost International flights in a full outbound passenger procedure, which will include checking the passenger's baggage in the HBS system for automatic checking. The inspection area for the hand baggage has been expanded, biometric passports have been added and nine exit gates have been opened. Duty-free shops and passenger dining complex were opened. The duty-free store mix will be similar
to the one in Terminal 3
Additional details
- Client
- Israel Airports Authority
- Project activities
- Management of planning, management of execution and supervision
- Project Area
- 15,000 Square Meters
- Financial Scope
- 60,000,000 NIS